GOVERNOR of Lagos State, Babajide Sanwo-Olu has announced the takeoff time for the construction of the 4th Mainland Bridge to begin in the First Quarter in 2023 and to be completed in 2026.
The state government, through the Office of Public Private Partnerships had, on Thursday, announced Messrs CCECC-CRCCIG Consortium as the preferred bidder for the construction of the bridge.
Sanwo-Olu, had at different fora assured residents to announce the preferred bidder before January 1, 2023.
Eight roads – Lagos/Ibadan Expressway, Lagos/Abuja highway, Benin/Sagamu, and Igbogbo/Lagos – would align with the bridge.
READ ALSO: HOW IPOB are ruining Southeast under the guise of fighting for BIAFRA (A MUST WATCH VIDEO)
The project, estimated to cost about $2.5 billion, would be delivered through Public-Private Partnership initiative and tolled for two years.
Special Adviser to the Governor on Public Private Partnerships, Mr. Ope George, and his couterpart in the Ministry of Works and Infrastructure, Engineer Aramide Adeyoye, disclosed this on Friday, during a press briefing in Alausa, Ikeja, Lagos.
According to George, the Fourth Mainland Bridge (4MB) Project, which is a proposed Public Private Partnership (PPP) transport infrastructure development, will comprise the construction and operation of a greenfield tolled road and bridge with a design speed of 120 kilometre per hour, including the development of adjacent real estates.
He added that the bridge, when completed, would become the second longest in Africa with three toll plazas, nine interchanges, a 4.5 kilometre Lagoon Bridge and an eco-friendly environment.
It is also expected to span about 37 kilometres, starting from Abraham Adesanya in Ajah, on the Eti-Osa-Lekki-Epe corridor and traverse the North West towards the Lagoon shoreline of the Lagos-Ibadan Expressway via Owutu/Isawo in Ikorodu.
READ ALSO: WIKE, others risk expulsion from PDP as they go for negotiations with Tinubu in UK
According to George: “You will recall that the Lagos State Government commenced a competitive bidding process for the selection of a concessionaire, by the issuance of the Request for Expressions of Interest (REOI) on 27th of November, 2019.
“A total of 52 responses were received with 32 being responsive.
“Subsequently, a Request for Quotation (RFQ) was issued on February 10, 2020 to the 32 eligible applicants and responses were received on 15th April, 2020 with a total of 15 responses.
“Upon evaluation, six bidders met the criteria to progress to the Request for Proposal (RfP) stage.”
George, explained that the bids have now been evaluated and Messrs. CCECC-CRCCIG Consortium emerged as the preferred bidder, while the Messrs. MOTA-ENGIL (NIGERIA &AFRICA), CCCC & CRBC CONSORTIUM, also shortlisted as the reserved bidder for the Fourth Mainland Bridge project.
READ ALSO: INSIDE LIFE: LADY gangraped to death on her birthday by male friends
Adeyoye added that the bridge will reduce congestion on the existing Carter, Eko and Third Mainland Bridges while opening new areas of the City for future developments.
She said the state government had carried along the over 48 estates, traditional rulers and others that would be affected by the bridge.
Adeyoye said the negative impact of the bridge was minimal compared to the advantages, urging those anxious for the project to take off to be patient and corporate with the contractor during the construction of the project.
READ ALSO: IPOB militants captured an Army Officer, strips him, waiting for execution (VIDEO)
4th Mainland Bridge construction: Lagos picks Chinese firm as preferred bidder
THE Lagos State Government, yesterday, announced Messrs CCECC-CRCCIG Consortium as the preferred bidder for the construction of the proposed Fourth Mainland Bridge project.
I’m APC woman I’m working for my in coming president Tinubu and shettima all the way come 2023 not can stop it in Jesus name Amen